Hempstead UFSD – Additions and Alterations at A.B.G. Shultz Middle School

Reporting period: November 2 – November 13, 2026

Overview

Over the past two weeks, work advanced across the building envelope, rooftop mechanical systems, interior MEP rough-in, and concrete placements in the new addition.

Building Envelope and Exterior

Windows and weatherproofing. VRD Contracting (GC Prime) framed the building fascia and closed in areas with Densglass. They began applying Blueskin to all window openings around the building and continued through the end of the report period.

Arrow Steel Windows received a large window delivery for the new addition on two different days.  Installation began on 11/12 with four carpenters putting in window frames on the first and second floors of the new addition.

Roofing. Demy Construction Systems laid out decking insulation and vapor barrier on the middle section of the new addition. They began adhering the second layer of roof insulation on the east side of the roof.

Roof drains. Hirsch & Company returned on 11/06 with two mechanics and began working on the roof drains. They continued this work through the end of the report period.

Mechanical. RMS Industries began installing sound attenuation inside the curbs for the rooftop AC units and continued through 11/09, when they completed it. That day they began installing hallway ceiling uni-vents.

Sheet metal. Blake Sheet Metal installed roof curbs for the AC units and continued installing ductwork on the first floor in the serving area.

Electrical. Relle Electric appeared only on 11/02, when four men continued roughing in power and lighting in the new addition. There are no later entries, so the schedule for their follow-on work is worth confirming.

York Concrete prepped the gym floor for concrete and poured the steps for the two stairwells on the north side of the addition.

City Gates Inc. made its first appearance on 11/13 with two men. They brought in materials and began installing steel columns for the cafeteria roll-up gate.

Hempstead UFSD | September 14 – October 23, 2026

Over the six-week period, the project moved from the tail end of structural and masonry work into interior rough-in and framing, with a steady and stable workforce. Manpower held at roughly 15 to 25 workers per day. The mix of trades shifted as the masonry scope finished, the roof steel was completed, and the mechanical, electrical, and plumbing (MEP) trades settled into a consistent rhythm.

Weeks 1–2 (September 14–25): Roof Framing, Masonry Close-Out, and Steel Decking

The period opened with the heaviest and most varied manpower. Giaquinto Masonry infilled block along the top of the NE stairwell under the decking and completed final cleanup and mortar touch-up. On September 17 the masonry was substantially complete, and Giaquinto left the site.

VRD Contracting, began framing the roof knee walls and patching decking on the second floor. Steel decking above the NE stairwell was completed, at which point VRD removed its equipment from the roof and had its lifts picked up by Sunbelt.

During this stretch, the MEP trades were in full rough-in mode:

  • RMS Industries (mechanical) roughed in heating and refrigeration lines on the second floor and hung ceiling-mounted electric space heaters in the girls’ locker room (two on September 18 and a final one on September 21).
  • Relle Electric roughed in power and lighting in the new addition and finished wiring the remaining cabinet heaters in the locker room by September 22.
  • Hirsch & Company (plumbing) ran water and waste lines on the second floor.
  • Blake Sheet Metal worked intermittently, installing ductwork on the second floor.

Weeks 3–4 (September 28 – October 9): Curtain Wall Framing and Ductwork 

VRD’s focus shifted to laying out and framing curtain walls on the first floor, starting on the west side on September 23. On September 24 an excavator was on site filling and compacting RCA for the gym sub-floor, and laborers began debris cleanup. VRD had steel workers open up the q-decking within the roof curbs for the air conditioning units. Blake Sheet Metal returned on September 25 and September 30 to set roof curbs.

Weeks 5–6 (October 12 – October 23): Steady-State Interior Work

VRD returned to a consistent crew of six, laying out and framing walls on the first and second floors. On October 12 they also installed the remaining paper towel and toilet paper dispensers and grab bars in the girl’s bathroom and shower area.

Relle, RMS, and Hirsch continued their rough-in work in addition without significant change.

The project advanced from structural close-out to interior build-out. The addition is now enclosed enough for framing, electrical, plumbing, and mechanical rough-in to proceed in parallel, with progress steady and no reported delays or safety incidents in the logs.

Work during this reporting period advanced the new addition’s framing, exterior enclosure, and mechanical, electrical, and plumbing installations. Key accomplishments included completion of steel decking above the northeast stairwell, substantial completion of masonry, and installation and wiring of additional heaters in the girls’ locker room area. 

During the week of September 14–18, VRD continued framing rooftop knee walls and patching first-floor decking. Installation of steel decking above the northeast stairwell began September 15 and was completed September 16. VRD also opened ceiling sections in the girls’ locker room to accommodate new heaters, and RMS installed the remaining three ceiling-mounted electric space heaters. 

Giaquinto completed block infill beneath the northeast stairwell decking, performed masonry cleanup and mortar touch-ups, and reported masonry substantially complete on September 17. 

During the week of September 21–25, VRD continued rooftop knee-wall framing and sheathing, and began exterior soffit framing and DensGlass installation. Layout and framing of the first floor west-side curtain walls began September 23 and remained ongoing through the end of the week. Additional work included placement and compaction of RCA for the gym subfloor. Laborers began and completed an extensive site cleanup of debris in and around the new addition on September 24 & 25. 

Work in the girls’ locker room progressed with RMS installing the final new ceiling-mounted electric space heater on September 21. That day, VRD closed ceiling areas around the three new heaters, and the next day Relle completed wiring the ceiling-mounted heaters. 

Mechanical, electrical, and plumbing rough-ins remained active throughout both weeks. RMS continued second-floor heating and refrigeration piping; Hirsch continued second-floor water and waste piping, and Relle continued power and lighting rough-ins throughout the new addition.

August 24–September 4, 2026

During this reporting period, work at ABGS Middle School focused on completing and preparing existing instructional and locker-room spaces for school use while advancing the new addition’s structure, enclosure, and building systems.

In rooms L2, L4, 207, and 209, contractors moved through the final stages of interior construction. Ceiling grids and tiles were completed, lighting and electrical devices were installed, and VCT flooring and cove base were finished. Casework, sinks, windowsills, temporary countertops, furniture, and classroom equipment were installed. The rooms were then cleaned, waxed, and arranged for classes. By September 1, casework in the existing rooms was substantially complete, and desks and tables had been assembled and placed.

The girls’ locker-room area also progressed toward completion. Ceiling work, locker and bench installation, epoxy flooring, plumbing fixtures, showers, and storage shelving were completed or substantially completed. Mechanical work continued with the installation of ceiling cabinet heaters, while the general contractor closed ceilings and installed partition hardware.

At the existing cafeteria, hazardous flooring and mastic were abated, followed by installation of a temporary VCT floor. This work supported continued school operations while the broader project remained active.

The new addition remained a major focus throughout the period. Masonry crews continued exterior insulation, brickwork, first-floor CMU walls, and second-floor mezzanine blockwork. Electrical crews coordinated closely with the masons to embed boxes and conduits in the new walls while continuing power, lighting, data, and fire-alarm work. Mechanical and plumbing contractors advanced heating, refrigeration, and water-line rough-ins, particularly on the second floor. Metal-stud framing also began on the roof, and a major delivery of roofing insulation and materials was received and placed on the roof.

Exterior access improvements advanced significantly. Steel work continued on the new outside stair serving the boys’ gym; by September 4, the remaining roofing over the stair has been installed, and the stair frame anchored to the building. Concrete crews formed and poured the boys’ locker-room entrance footings and steps, the kitchen-door ramp and walkway, and the cafeteria exit ramp. Required rebar, concrete, grout, CMU, and brick inspections were performed alongside this work. 

Work completed or substantially completed

  • VCT flooring in L2 and L4

  • Ceiling tile in L2, L4, 207, and 209

  • Cove base in the four instructional rooms and kiln rooms

  • Casework in the existing rooms

  • Classroom furniture assembly and setup

  • Girls’ locker-room epoxy flooring

  • Girls’ locker-room center lockers, benches, and plumbing fixtures

  • Partial cafeteria flooring and mastic abatement

  • Temporary cafeteria flooring

  • Concrete for several exterior entrances, ramps, steps, and walkways

  • Data-port labeling and ongoing fire-alarm testing

  • Installation of sinks in L2, L4, 207, and 209

Work continuing beyond September 4

  • Second-floor mezzanine CMU construction

  • Roof-level metal-stud framing

  • Electrical, plumbing, heating, and refrigeration rough-ins in the new addition

  • Completion of the boys’ gym exterior stair

  • Roofing operations

  • Final closeout, cleanup, hardware, and remaining finish work in renovated areas

Overall, the period marked a transition in the existing building from active construction to classroom and locker-room readiness, while work on the new addition continued through masonry, framing, roofing, and MEP rough-in phases.